Commissioning LEV for a New Production Line

Commissioning is the moment a new LEV system proves it works - and sets the numbers every future test is judged against. Before a new production line runs in earnest, an engineer measures the airflow and pressures at every hood, confirms the system is balanced, and records that baseline in a commissioning report you keep for the life of the kit.

Every hood
Measured
Flow
And pressures
Balance
Across the system
Baseline
Recorded
Report
Kept for life
Then
14 mo cycle
FLOWPRESSUREBASELINE SETNEW LINECOMMISSION
TR19 certificate Before & after photos Filters degreased Fully insured EHO accepted

The short answer

Commissioning is the moment a new LEV system proves it works - and sets the numbers every future test is judged against. Before a new production line runs in earnest, an engineer measures the airflow and pressures at every hood, confirms the system is balanced, and records that baseline in a commissioning report you keep for the life of the kit.

The detail

What commissioning a new line involves

When a new production line goes in, its extraction has to be commissioned before the line is relied on - and commissioning is far more than switching the fan on and watching dust disappear. HSE guidance is specific: commissioning assesses control and demonstrates whether the LEV adequately controls exposure to the substances it is meant to capture. It is the formal proof that what was designed and installed actually performs, on this line, in this building.

The core of it is measurement at every hood. An engineer records the airflow and the static pressures across the system, confirms that capture velocity at each source is enough to draw the contaminant in, and checks that the system is correctly balanced - so that opening one hood does not starve another. Where a line has many capture points, balancing is what stops the far hoods being quietly under-served by the ones nearest the fan.

Those figures become the benchmark. Commissioning defines the performance targets - the flow rates and pressures - that every future thorough examination, and all the maintenance in between, will be judged against. Without them there is no reference point: a later test can measure the system but cannot say whether it has drifted, because there is nothing to compare it to. This is why a missing commissioning baseline is one of the first gaps an examiner flags.

All of it is captured in a commissioning report. HSE expects this to record the system's general condition and operating conditions at commissioning, the configuration and components - fan specification, filter media, waste collection, make-up air and discharge arrangements - photographs of the key parts, and the methods used to judge performance, from airflow and pressure measurements to smoke tests and dust lamps. It should be written so you can actually understand the results, and kept for the life of the equipment.

What it means for you

Why the baseline is worth getting right

A well-commissioned line starts its working life with proof it controls exposure and a clear datum for everything that follows. The fourteen-month thorough examinations become meaningful comparisons rather than standalone snapshots, maintenance is targeted at holding the baseline, and any drift shows up early against a known starting point. The value of commissioning is felt every year afterwards.

Skipping it, or accepting an installation without a commissioning report, stores up trouble. The line may control exposure or it may not, and there is no way to demonstrate which - to an inspector, an insurer or the workforce. The first thorough examination then has to establish a baseline retrospectively, on a system that has already been running, which is a weaker position than commissioning it correctly from new.

Commissioning a new production line properly is, in short, how you turn a designed-and-installed system into a proven one with a documented reference point. It is the bridge between buying extraction and being able to show it works - and the foundation the whole examination and maintenance regime is built on.

Every hood
measured
Baseline
the datum
Report
kept for life

The service behind the guide

Sibling guides

Read next

Keeping LEV records your insurer will accept · The link between LEV, ventilation and air quality · Building a maintenance schedule that holds up

Questions

Frequently asked questions

What is LEV commissioning?

It is the formal check that a new or modified system actually controls exposure. An engineer measures airflow and pressures at every hood, confirms the system is balanced, and records the results as a baseline.

Why does a new line need commissioning before use?

Because it proves the installed extraction performs as designed on that line, and sets the benchmark figures every future examination and maintenance task is judged against. Without it there is no reference point.

What goes in a commissioning report?

The system's condition and operating conditions, its configuration and components, fan and filter details, make-up air and discharge arrangements, photographs, and the methods and results used to judge performance.

How long should the commissioning report be kept?

For the life of the equipment. It is the datum every thorough examination compares against, so it stays relevant for as long as the system runs.

What happens if a system was never commissioned?

There is no baseline to judge drift against, so the first thorough examination has to establish one retrospectively on a system already in use - a weaker position than commissioning from new.

20+ Years of Experience

Phoenix Duct Clean · by the numbers

Kitchen canopies
degreased
4,287
Laundry ducts
cleaned
1,877
LEV systems
tested
1,658
Hours
on site
54,754

Book your LEV thorough examination and test

Phoenix carries out LEV testing to HSG258, with clear reports, honest remedial advice and records your insurer and inspector will accept. Call or email for a quote.